The
Vietnamese had discovered a large gas field – Bach Ho- in the southern waters
some 200 miles from Saigon and were very keen to develop it as soon as possible
to help their faltering economy. But they were having difficulty in negotiating
a contract with the international oil company, British Petroleum, the operator
of the field. It had been three years since the gas discovery and the two parties could not even agree on the basics of the problem. It was always one step forward and two back.
The
World Bank deputized me to go and assist the Vietnamese government in these
negotiations and to help get the project off the ground. Before I set out on this assignment, I was told half facetiously by my colleagues with greater experience of Vietnam that " there was a right way, and there was a wrong way and then there is the Vietnamese way". I should have heeded that advice.
My
earliest efforts to help the government were directed at organizing seminars
and training courses on gas reservoir assessment and management and
contract negotiations. I was also able to dragoon my colleagues into delivering lectures and leading discussions.
Over the next few years, the younger professional staff in Petrovietnam would often come to me for advice and I
would give them papers and discuss how they could proceed in their negotiations
of the gas contracts.
It
was a complicated problem since most of the gas from the Nam Con Son field some two hundred miles offshore HCMC was best used for power generation,
since the only other use was for the more costly process for the manufacture of
fertilizers. The integrated value chain of gas field development, offshore
pipeline,
power generation plant and then distribution of electricity required that a number of problems be
solved at the same time. BP would not invest $1 billion in the
development of the offshore gas field until they were assured of an
economically viable price for the gas. The new offshore pipeline consortium
wanted to ensure that there was adequate annual throughput of gas with an
economical transport charge. The power generation plant owner wanted guarantees
that the gas price would be such that after its conversion to electricity, the
electricity price would cover his costs and provide a profit.
The
real problem arose in determining the electricity price. Since there was only one national
utility, Electricity of Vietnam (EVN),
the price was determined by the government on an annual basis. But all the
upstream parties needed assurances about the level and gradual increase of the
electricity price over the next twenty years. As it was, the current price of
electricity was too low and would not cover the costs of developing the gas field and pipelines. To further
complicate the issue, the government had decided that the investments in the
power plant were too rich for their tastes and wanted to invite the private
sector to come in on a “build- operate- transfer” BOT type contract. They looked to the Bank to provide the guarantees to cover the
risks and to help them mobilize the $500 million needed for the power plant.
Furthermore, there was no central agency to negotiate these contracts: the gas
contracts were the responsibility of Petrovietnam, while the power plant was handed over to
the ministry of industry rather than to EVN to develop.
Resolving
these issues held another piquant note for me. I remembered that this was the
same field that Vietnam had allocated to ONGC some years ago. Actually, negotiations
for this block had started in 1982 when I had invited a team from Petrovietnam to see what we had achieved in Bombay High. In these meetings, they had urged
ONGC to come to Vietnam and I had countered that they should give us two
blocks, one in the Bach Ho block and the other in deeper waters or
the Nam Con Son block. Apparently, these inter
governmental negotiations had carried on for some years until ONGC had been
given the NCS block in 1987. ONGC had drilled the first well in 1989, but it
turned out to be dry. The second well had encountered a blow out and ONGC, then
led by S.L. Khosla,
a civil servant with financial background, had decided to cut their losses and
to sell 25% of the block to a combination of BP and Statoil of Norway. They also handed
over the operating authority to BP. BP had gone back to the same field and
their new discovery was in a block that was still majority owned by ONGC.
It was to take a good five years before
we could untangle this mess. I had started by focusing on the weakest link –
the electricity price – since this was an area of public
policy and the Bank had leverage. It had lent almost $400
million to the power sector on the condition that the electricity pricing had
to be remunerative for EVN.
At every opportunity, I stressed upon the Ministers and the Deputy Prime
Minister, the need to comply with their obligations in their existing contracts
with the Bank, but also to issue a statement of intent regarding the underlying
principles of pricing. In fact, at the negotiation of the next $220 million
power project loan from the Bank, I curtailed the meeting until the Vietnamese
side produced a written statement from the Prime Minister’s office in regard to
their policy on electricity pricing. With this in hand, we could now ensure
that there were adequate margins for all the upstream players.
We
had encouraged the government to float an open tender for the power plant under
a BOT type contract. In this type of contract,
the private sector provided the funds to build the power plant, operated it for
a period of twenty years and then transferred it to the government. This was
just a few months after the Asian crash of 1997. Everyone was sure that there
would be no bidders; after all, big hitters like Indonesia and Thailand were canceling their
existing plans. My view was that these cancellations in neighboring countries
could only benefit Vietnam,
as it would remain the only game in town for the equipment suppliers. True
enough, as many as seven international bidders submitted their bids and their
prices were within 10% of each other, and these at one of the lowest levels in
the region.
Now
began the tedious process of selecting the winner and negotiating the power
contracts. Once these were in place, the interrupted negotiations on the gas contracts could be resumed with some
assurance of success. It was, after all, a $2 billion project for a country
whose total GDP was no more than $20 billion. Finally, six years after the gas
discovery, the gas contracts were signed, and construction work began on the
offshore platforms and pipelines.
The power plant negotiations still
needed to be concluded with EdF, the French national utility that had won the
contract. Since the Ministry of Industry had never negotiated a contract of
this magnitude nor of this type, the process was tortuous and slow. The Bank could not help the government because
under our charter these negotiations had to be done directly by the
government. So I mobilized funds
from different sources to hire lawyers and experts to assist them. But the
level of distrust between the government and the private sector was so great
that every concession was viewed with extreme suspicion. And there were many an
occasion when both sides were ready to give up.
Survival
and ingenuity among the Vietnamese were evident everywhere you looked. The
government had decided to build a road around the Truc Bach Lake in front of our apartment building.
The road would be built and when it encountered a house that presented an
obstruction, it would simply skip to the other side of the house and continue
the construction. After about nine months, we were presented with the bizarre
sight of a road that ringed the lake, but was interspersed with houses that
blocked any smooth movement. It turned out that instead of waiting for the
consent of all the house owners, the government had simply decided to go ahead
till the house owners realized the futility of holding on and settled for the
best deal they could negotiate. Although work had commenced with great aplomb,
it became apparent to me that three completely different methods of
construction were being used. This was the Vietnamese method of determining the
most cost effective approach by actual trial and error. Watching the
construction of this road was good education for me on how the Vietnamese often
approached problems –“step by step” or “crossing the river by feeling the
stones.” The government seemed to be using the same principle in their attempts
to bring the gas discovery to the shore.
I
urged the Vietnamese to look to the future and take some risks in their
negotiations. There is a Vietnamese legend that there is a sacred turtle that lives in Hoan Kiem Lake in Hanoi, which emerges in times of danger to the
Vietnamese people. Legend had it that when all seemed lost, the turtle had
emerged with a sword in its mouth, which King Lien had used to defeat his enemies. I used
the turtle as my metaphor for the problems in the country.
“You
are,” I would say, “very similar to the sacred turtle that you worship. Like a turtle, you are
persistent and never give up even in the face of the direst circumstances. The
turtle has a thick skin enabling him to absorb outside influence without
disturbing the core of its being. You, too, listen to advice and much criticism
from all over, but still manage to retain your own point of view. The turtle,”
I would further point out, “is the only animal that cannot go backwards. But,
remember,” I would continue, “it can go around and around in circles.” There
would inevitably be lots of chuckles of laughter at this as this was translated
for the audience. “Anyway, remember,” I would end, “that the turtle only
advances when it sticks its neck out .”
The
turtle story was to become my signature speech
and often the Vietnamese from the audience would stroll over to me after the
talk and shake their heads in agreement. Some of them would counter with the
Vietnamese proverb about crossing the river by “feeling the stones” and “moving
step by step”. “If the river is deep,” I would rebut, “all you will achieve is
to drown step by step. Sometimes you have to take a leap.”
During
this time, Petrovietnam,
BP, Edf
negotiators would often visit me informally as well as the Ministry officials,
each with their own version of the issues that were bedeviling their
negotiations. Each threatened to pull out of the project on an almost monthly
basis. Finally, we were able to put all the pieces in place and the power plant
project was signed as well. Gas flowed from the Nam Con Son (NCS) gas field in December 2003. This marked a
significant achievement – Vietnam had managed to attract $500 million of
private investment while the rest of the Asian countries were still in crisis,
and it had also successfully negotiated a gas contract with an international major. Clearly, the government was
serious in its desire to attract private investment that it said it desperately
needed. The NCS project was proof of the government’s determination and
willingness to make the necessary compromises to get there.
Many years later, when I
was saying farewell to Vietnam,
Dr. Hiep, the Senior
Vice President of Petrovietnam,
arrived with an embroidery painting as a present from his institution. The
picture was of an old village schoolmaster.
“That is how Petrovietnam
saw you,” he said.
“ You have been our teacher and taught us so much over the past ten years and for which we you so
much.”
Needless to say, that
painting remains one of my prized possessions to this day.
A very interesting account of this gas development in Vietnam- and relevant for other countries, including Bank staff too, working in SSA
ReplyDelete